Posts were set into cement, then framing added and painted. The materials used were left over materials from the rehab.
Steven cut the hole in the decking for the posts to fit through. The decking was rescued when a neighbor replaced his decking. The back side was used and sanded.
Steven finished edges and other details on the roof. Because we were both getting hip replacements this summer, we hired someone to climb on the roof and install the last roof edges and trim.
We changed the position of the door to the kitchen porch and then needed to remove the cement steps. Steven rented a jack hammer but even then it was a huge job and not finished in one day. We took the large pieces and made a perimeter in the back of the house.
We had purchased 3 slider windows on clearance thinking that would be enough but because of the existing posts we needed one more. We ordered it and when it came it was missing an exterior piece. We installed it temporarily for the winter.